Higher Education

EMORY UNIVERSITY

THE DONNA AND MARVIN SCHWARTZ

CENTER FOR PERFORMING ARTS

Owner

Emory University

Architect

Michael Dennis & Associates

Engineer

Cossentini Associates

Contract Type

Negotiated

Square Footage

 67,000

Description

The building was provided with seven air handling units dedicated to the following specific areas: concert hall seating, concert hall stage, lab theater, instrument rehearsal, dance area, lobbies and back stage. The A/C systems were medium pressure VAV type to be able to provide strict temperature and humidity control of the spaces. All air handling units were installed in the two dedicated mechanical rooms located in the basement.

The chilled water and steam for preheat and cooling coils as well as steam for the humidifiers were provided from the Emory campus physical plant. Two pressure reducing stations were implemented to use low pressure steam in the building.

All systems serving the sound-critical areas were provided with sound attenuation equipment. The air distribution systems were incorporated into the architectural background to minimize the aesthetic impact.

Mechanical and support areas were provided with spot cooling using several fan coil units.

The mechanical room was provided with a condensate pumping system to return the condensate back to the main physical plant.

Equipment List
  • 1 27,000 CFM AHU
  • 1 21,000 CFM AHU
  • 1 20,000 CFM AHU
  • 1 15,000 CFM AHU
  • 1 11,000 CFM AHU
  • 1 8,000 CFM AHU
  • 1 6,500 CFM AHU
  • 62 VAV Terminal Units
  • 4 Unit Heaters
  • 3 Cabinet Unit Heater
  • 2 310 GPM Hot Water Pumps
  • 2 310 GPM Heat Exchangers
  • 15 Fan Coil Units
  • 5 Relief Exhaust Fans

 

EMORY UNIVERSITY

NELL HODGSON WOODRUFF SCHOOL OF NURSING

Owner

Emory University

Architect

Stang & Newdow/ Ayers, Saint, & Gross

Engineer

Barrett Woodyard

Contract Type

Negotiated

Square Footage

 91,000

Description

The project included two new buildings, the Pavilion three-story building and the Administration building with five stories.

The Pavilion building has been provided with air conditioning systems to serve the auditorium, case study auditorium and the classrooms on the third floor. The Plaza level amphitheater was provided with dedicated constant volume air system.

The other two floors were equipped with medium pressure VAV type air handling system. The air was distributed using parallel and series type power induction units equipped with hot water reheat coils. The plumbing system provided waste and vent system to the toilets’ mechanical rooms and admin areas. Hot water, cold water and hot water recirculation piping systems were installed to support the toilets and the other miscellaneous users.

The Administration building has been provided with air conditioning systems to serve the classrooms, laboratories, lounges, offices, and support areas located on the five floors.

All air handling units were equipped with cooling, heating and filtration capabilities. The units were provided with common outside air shaft. The OA was delivered by one supply fan provided with filtration capability and variable frequency drive to match the demand of all units at any time.

The air handling units were medium-pressure VAV type. The air was distributed on all floors using fan-powered units equipped with hot water reheat coils. The telecommunication rooms located on each floor were equipped with dedicated fan coil units to match the cooling demand and maintain the operational status of the room.

The chilled water was supplied by the campus Micheal Street energy plant.

To satisfy the demand for heating hot water for the Pavilion and the Administration buildings, a new steam-fired shell and tube heat exchanger was installed. New hot water, end suction type circulation pump was provided.

The plumbing systems included waste and vents, cold water, hot water, and hot water recirculation systems for the toilets, break rooms, lounges, and mechanical rooms. Electric domestic hot water heaters were provided.

Research Facility Equipment List
  • 1 11,609 CFM AHU
  • 1 11,178 CFM AHU
  • 1 11,165 CFM AHU
  • 1 10,910 CFM AHU
  • 1 10,188 CFM AHU
  • 1 7,570 CFM AHU
  • 1 5,423 CFM AHU
  • 1 5,366 CFM AHU
  • 5 820 CFM Fan Coil Units
  • 1 700 GPM Hot Water Pump
  • 1 13,365 CFM Inline Centrifugal Fan
  • 1 2,800 CFM Inline Centrifugal Fan
  • 1 2,335 CFM Inline Centrifugal Fan
  • 1 8,345 CFM Centrifugal Blower
  • 3 510 CFM Exhaust Fans
  • 1 400 CFM Exhaust Fan

 

EMORY UNIVERSITY

GENETICS MOLECULAR MEDICINE RESEARCH

(DENTAL SCHOOL)

Owner

Emory University

Architect

Lord, Aeck, & Sargent

Engineer

Nottingham, Brooke, & Pennington 

General Contractor

McCarthy Building Companies

Contract Type

Negotiated

Square Footage

60,000

Description

The scope of the project included the complete renovation of the fourth floor of the Emory University School of Medicine. Also included was the extensive renovation of the fifth floor penthouse.

The new floor layout included several wet and dry laboratories, isotopes laboratories, two BSL-3 laboratories, decontamination room, offices, microscope, computer and dark rooms.

Most of the laboratories included fume hoods or bio-safety cabinets or both.

The equipment provided for this project included:

  • Fume and isotope hoods
  • Sterilizers
  • Glassware washers, dryers
  • Autoclaves
  • Freezers and coolers


The project included selective demolition of the existing laboratory areas, mechanical chases, and removal of the existing mechanical systems and air distribution systems.

The new mechanical system consisted of the following pieces of equipment:

  • New air handling unit, 100% outside air, medium pressure, VAV system. The system was also provided with VAV boxes with hot water reheat coils.
  • Dedicated VAV exhaust system served by two high-velocity discharge fans, running
    concurrently, each capable of handling 60% of the nominal load. The system was provided with pressure-independent air valves and a stainless steel welded ductwork network.


The fourth-floor VAV system has a dual purpose. One is to provide cooling or heating of the entire floor, and the second is to provide make-up (displacement) air for the equipment that needs exhaust.

To reduce energy consumption, the system was provided with an enthalpy energy recovery wheel to extract the energy from the exhaust system and transfer it to the outside air stream.

The new plumbing system included:

  • Acid-resistant waste and vent system
  • Sanitary waste and vent system
  • Domestic hot and cold water with hot water recirculation
  • Specialty gas systems, including vacuum, lab air, natural gas
  • CO2 local distribution system, including the cylinders and the distribution manifolds
  • Laboratory sinks and cup sinks
  • Fixtures for the toilets
  • Emergency showers and eye wash stations
  • Cold, hot, steam and DI water for the equipment listed.
  • The bio-safety cabinets were equipped with normally closed, delayed action natural gas safety valves and normally open vent valves to operate on a 30- minute duration.
  • The liquid nitrogen system consisted of cryogenic units, a manual fill station, a piping system, shut-off valves, and a phase separator branch with a cryogenic valve.    
Equipment List
  • 1 –  23,750 CFM AHUs
  • 49 –  150 to 1,280 CFM Terminal Units
  • 31 –  150 to 1,400 CFM Lab Exhaust Regulators
  • 2 –  13,750 CFM Fume Exhaust Fans
  • 1 –  23,750 CFM Steam Humidifier
  • 5 –  Biological Safety Cabinets
  • 11 –  Fume Hoods
  • 3 –  Isotope Hoods
  • 44 –  Laboratory Cup Sinks
  • 24 –  Laboratory Sinks
  • 9 –  Emergency Eye Wash Stations
  •  4 –  Emergency Showers